Events Cancelled due to Covid-19? Use of force Majeur Clause

Covid-19 (coronavirus) has a practical impact on many Horizon 2020 projects, as project meetings and events get cancelled all around Europe.

But how to deal with the eligibility of the costs (event, flight, hotel etc.) in case of cancelled meetings. Are the costs for canceling eligible within the H2020 project (force majeure)? This question was asked to the Legal and Financial Helpdesk, find below the answer.

Article 51 of the H2020 Model Grant Agreement (H2020 MGA) sets out the general framework and conditions in which the force majeure clause can be used. As a general rule under H2020, in case of force majeure, a party will be excused from not fulfilling its obligations (i.e. there will be no breach of obligations under the GA and none of the adverse measures for breach will be applied). Costs will be eligible, if they fulfil the general eligibility conditions like any other costs incurred under the action. However, if force majeure entails extra costs for the implementation of the action, it will normally be the beneficiary who must bear them.

Having said that we are aware that indeed the outbreak of Corona virus in the EU and elsewhere may have implications for the participation of individuals in meetings and events organised by beneficiaries for the purposes of H2020 ongoing actions and for their implementation. For instance, it may prevent beneficiaries to fulfil their obligations under the action or even to carry out work in a zone affected by the virus. It may also force beneficiaries to cancel a meeting due to the unavailability of key staff or because most of the participants cannot attend.

If such a situation occurs, beneficiaries must immediately inform the Project Officer, which will examine on a case-by-case basis the possible application of the rules on force majeure, in the meaning of Article 51 of the H2020 MGA.

Example: Beneficiaries cannot attend meetings or events related to the action because of their recent contact with someone suffering from the virus or their presence in an area considered to be at high risk. Costs of travel or accommodation that could not be cancelled and which are not reimbursed from other sources could be eligible (provided that the cost eligibility conditions are fulfilled, notably that meeting was necessary for the action, the costs were reasonable and in line with the usual practices of the beneficiary on travel) even if the beneficiary did not travel and did not take part in the meeting/event.

 

Check out rmore info about Covid-19 impact in the EC website: 'the corona virus response team'

And in the Funding & Tenders portal here

 

source

My Tweets

H2020 in Brussels NCP_Brussels H2020 in Brussels

Europa wil jouw stem horen over de nieuwe klimaatmissie. Wil jij je mening geven? Schrijf je dan in (… https://t.co/EZSrb91iD9

15 Jul Reply Retweet Favorite
Marc Vanholsbeeck MVanholsbeeck Marc Vanholsbeeck

@EU_Commission veut connaître l'opinion des citoyens sur la #MissionClimateAdaptation. Inscription… https://t.co/iqbtjcywsq

14 Jul Reply Retweet Favorite
H2020 in Brussels NCP_Brussels H2020 in Brussels

La Commission Européenne veut connaître l'opinion des citoyens sur la nouvelle #MissionClimateAdaptation. Inscrivez… https://t.co/HsOd5J083b

13 Jul Reply Retweet Favorite
Camille Lepinay CamilleLepinay Camille Lepinay

@NCP_Brussels https://t.co/nrJLc1tI9s

13 Jul Reply Retweet Favorite
Camille Lepinay CamilleLepinay Camille Lepinay

something to follow up closely @EuropeBrux @ecobuild_bxl @NCP_Brussels @GreenlabBru https://t.co/UbI3Qms4jH

13 Jul Reply Retweet Favorite